Maryborough Water Quality Enhancements – Mechanical Installation

Project Overview

Client : Veolia Water Services

Date : September 1, 2016

Info : Water Treatment Plant Upgrade

Description of Works

SALT REDUCTION BUILDING – INTERNAL AREA

  • SRU RO units installations
  • Connections into RO Blend Stream
  • Potable Water Supply connections
  • Air lines supply connections
  • FRP channel grate covers installation

SALT REDUCTION BUILDING – CHEMICAL AREA

  • Neutralisation Tank Installation
  • Citric Acid Tank Installation
  • Anti-Scalant Tank installation
  • Biocide Storage Tank installation
  • Potable Water Supply connection
  • SRU Standby Back-up Generator installation.

FILTER GALLERY

  • Relocation of existing Clear Water Sump Pump
  • Filtered treated water pipeline installation
  • Treated Permeate water return (from SRU) installation
  • Backwash pump & pipeline installation
  • Post-dose Chlorine installation
  • Free Chlorine sample point installation
  • Pre-SODA ASH dose point installation
  • Post-dose Ammonia installation