Maryborough Water Quality Enhancements – Mechanical Installation
Project Overview
Client : Veolia Water Services
Date : September 1, 2016
Info : Water Treatment Plant Upgrade
Description of Works
SALT REDUCTION BUILDING – INTERNAL AREA
- SRU RO units installations
- Connections into RO Blend Stream
- Potable Water Supply connections
- Air lines supply connections
- FRP channel grate covers installation
SALT REDUCTION BUILDING – CHEMICAL AREA
- Neutralisation Tank Installation
- Citric Acid Tank Installation
- Anti-Scalant Tank installation
- Biocide Storage Tank installation
- Potable Water Supply connection
- SRU Standby Back-up Generator installation.
FILTER GALLERY
- Relocation of existing Clear Water Sump Pump
- Filtered treated water pipeline installation
- Treated Permeate water return (from SRU) installation
- Backwash pump & pipeline installation
- Post-dose Chlorine installation
- Free Chlorine sample point installation
- Pre-SODA ASH dose point installation
- Post-dose Ammonia installation